PROGRESS REPORT AS ON 22.9.2010
S.
No
|
Name of Work
|
Estimate Cost
|
Executing Agency
|
Stage of
Work
|
Remarks
|
1.
|
Amphi Theatre at New Summer Festival Ground
|
42.00
|
Project Director, D.R.D.A., Vellore-9.
|
Completed.
|
--
|
2.
|
Watch Tower with boat jetty at Nilavour
|
19.71
|
Project Director, D.R.D.A., Vellore-9.
|
Completed
|
--
|
3.
|
Beautification of Path and Drive way to Boating lake at Punganoor
|
83.63
|
Project Director, D.R.D.A., Vellore-9.
|
Completed
|
--
|
4.
|
Auditorium at New Summer Festival Ground
|
40.43
|
Project Director, D.R.D.A., Vellore-9.
|
Completed
|
--
|
5.
|
Information Kiosks, Beautification of entrance and toll gate
|
20.45
|
Project Director, D.R.D.A., Vellore-9. (Kattidamaiyam)
|
Completed
|
--
|
6.
|
Deepening the lake widening of Foot Path alround the lake and strengthening the lake bund
|
55.36
|
Project Director, D.R.D.A., Vellore-9.
|
Completed
|
--
|
7.
|
High mast lighting in and around the lake & Street Light Provision
|
27.77
|
BDO, Jolarpet.
|
Completed
|
--
|
8.
|
Construction at Hanging Pedestrain bridge at hanuman temple before hair pin bend No 8 in Elagiri Hills
|
17.30
|
Project Director, D.R.D.A., Vellore-9.
|
Completed
|
--
|
9.
|
Construction of Trekking shelter on Jalagambarai Nilavoor Trail with Camping facilities 3 units Elagiri Hills
|
2.10
|
District Forest Officer Tirupathur
|
Completed
|
--
|
10.
|
Construction of Rain Shelter 1 unit at hairpin bend No 9 in Elagiri Hills
|
0.70
|
District Forest Officer Tirupathur
|
Completed
|
--
|
11.
|
Development of view point at Karadi munai in Elagiri Hills
|
1.90
|
District Forest Officer Tirupathur
|
Work in progress
|
--
|
12.
|
Adventure & Sports facilities at Elagiri hills
|
11.75
|
Project Director, D.R.D.A., Vellore-9.
|
Completed
|
--
|
13.
|
Adventure & Sports facilities providing swimming pool at Elagiri Hills
|
18.62
|
Project Director, D.R.D.A., Vellore-9.
|
Completed
|
--
|
14.
|
Fencing using weldmesh with L Angle post alround boating lake at Elagiri Hills
|
18.00
|
Project Director, D.R.D.A., Vellore-9.
|
Completed
|
--
|
15.
|
Fencing Using Weldmesh with L Angle post alround Yatri Nivas and information centre (Kattidamaiyam) at Elagiri Hills
|
6.00
|
Project Director, D.R.D.A., Vellore-9.
|
Completed
|
--
|
Total
|
365.72
|
State Funded Scheme 50 %, (Tourism Department Sanction )
G.O Ms.No 182 Tourism & Culture Department (T3) Progress Report as on 22.9.2010
Infrastructure Facilities to Elagiri Hills
S.
No
|
Name of Work
|
Estimate Cost
(in lakhs)
|
Executing Agency
|
Stage of
Work
|
Remarks
|
1
|
Providing CC pavement at Athanavoor to Pallakanniyur Km 0/0-1/9 in Elagiri Hills
|
41.90
|
Project Director, D.R.D.A., Vellore-9.
|
Work Completed
|
--
|
2
|
Nilavoor to Pallakaniyur BT Road 0/0-2/0
|
35. 90
|
Project Director, D.R.D.A., Vellore-9.
|
Work Completed
|
--
|
3
|
Nilavoor Boat House foot path around
|
10.90
|
BDO, Jolarpet
|
Work Completed
|
--
|
4
|
Information centre to summer festival ground foot path 800 M
|
21.50
|
Project Director, D.R.D.A., Vellore-9.
|
Work Completed
|
--
|
5
|
Nilavur Boat House around retaining wall
|
22.15
|
BDO, Jolarpet
|
Work Completed
|
--
|
6
|
Nilavur Boat House around fencing work
|
8.50
|
BDO, Jolarpet
|
Work Completed
|
--
|
Total
|
140.85
|
POOLED ASSIGNED REVENUE SCHEME 2008-2009
Sl.
No.
|
Name of the Habitation
|
Name of the Work
|
Estimate Amount
(Rs. in lakhs )
|
Stage of Work
|
1.
|
2.
|
3.
|
4.
|
5.
|
1.
|
Elagiri Hills
|
Construction of Check Dam in Erimeri vattam in Nilavoor
|
2.92
|
Completed
|
2.
|
Elagiri Hills
|
Construction of Check Dam in Melarikottai in Mangalam
|
6.42
|
Completed
|
3.
|
Elagiri Hills
|
Construction of Check Dam in Thayalur
|
8.25
|
Completed
|
4
|
Elagiri Hills
|
Construction of Check Dam in Alamarathuvattam
|
5.65
|
Completed
|
5.
|
Elagiri Hills
|
Construction of Check Dam in Manjankollai Pudur.
|
6.50
|
Completed
|
6
|
Elagiri Hills
|
Construction of Check Dam in Muthanur Odai.
|
7.32
|
Completed
|
7
|
Elagiri Hills
|
Construction of Check Dam in Military Camp in Mettukaniyur
|
8.25
|
Completed
|
8
|
Elagiri Hills
|
Construction of Check Dam in Melarikottai Vt.near Eswaran koil.
|
8.25
|
Completed
|
9
|
Elagiri Hills
|
Construction of Check Dam in Rayaneri.
|
6.50
|
Completed
|
10
|
Elagiri Hills
|
Construction of Check Dam in Kottur Ebinesar School back
|
7.32
|
Completed
|
11
|
Elagiri Hills
|
Construction of Check Dam in Aurovil near Leemeridian in Kottur.
|
8.25
|
Completed
|
12
|
Elagiri Hills
|
Construction of Check Dam in Ambalathupallam in Pallakaniyur.
|
8.75
|
Completed
|
13
|
Elagiri Hills
|
Construction of Check Dam in Puthur in Padanoor Village
|
8.75
|
Completed
|
14
|
Elagiri Hills
|
Construction of Check Dam in Erimeri vattam in Puthur.
|
14.11
|
Completed
|
15
|
Elagiri Hills
|
Construction of Check Dam in Thayalur Burial Ground
|
8.75
|
Completed
|
16
|
Elagiri Hills
|
Construction of Check Dam in Near in Mangalam Burial Ground
|
8.75
|
Completed.
|
17
|
Elagiri Hills
|
Construction of Check Dam in Karikkuthi Eri in Athanvur Village
|
8.75
|
Completed
|
Page -2
POOLED ASSIGNED REVENUE SCHEME 2008-2009
Sl.
No.
|
Name of the Habitation
|
Name of the Work
|
Estimate Amount
(Rs. in lakhs )
|
Stage of Work
|
18
|
Elagiri Hills
|
Beautification & improvements to Mangalam Eri Boat House and Park
|
15.44
|
Completed
|
19
|
Elagiri Hills
|
Beautification & improvements to Nilavur (Kotooran ) Eri
|
15.42
|
Completed
|
20.
|
Elagiri Hills
|
Beautification & improvements to Manjankollai Eri Boat House and Park
|
12.20
|
Completed
|
21
|
Elagiri Hills
|
Providing CC road to Mangalam Samartian School to K.Vattam Road
|
12.33
|
Completed
|
22.
|
Elagiri Hills
|
Providing CC road to Manjankollai to Krishnan Vattam
|
26.50
|
Completed
|
23.
|
Elagiri Hills
|
Providing CC road to Manjankollai to Krishnan Vattam
|
2.12
|
Completed
|
24.
|
Elagiri Hills
|
Construction of Check Dam in 30 mt length Mangalam Melkollai (near Ex.president land)
|
8.85
|
Completed
|
25.
|
Elagiri Hills
|
Construction of Oor Eri in Athanavoor.
|
14.22
|
Completed
|
Total
|
240.57
|
TOURISM DEVELOPMENT WORKS
G.O.No 160 Tourism and Culture (S3) Department Dated : 4.9.2008
PROGRESS REPORT AS ON 22.9.2010
SHOLINGHUR SHRI LAKSHMI NARASIMA SWAMY TEMPLE
TOURISM CONTRIBUTION Rs.16.18 Lakhs, H & RC Contribution : Rs.36.19 Lakhs.
S.
No
|
Name of Work
|
Estimate Cost
|
Executing Agency
|
Stage of
Work
|
Remarks
|
1
|
Car Parking at Chinna Malai Adivaram
|
11.75
|
Hindu Religious & Endowment Board
|
Work Completed
|
--
|
2
|
Car Parking at Periya Malai Adivaram
|
5.47
|
Hindu Religious & Endowment Board
|
Work Completed.
|
--
|
3
|
Construction of Toilet Block at Chinamalai,
|
2.25
|
Hindu Religious & Endowment Board
|
Work Completed
|
--
|
4
|
Construction of toilet at 620th Step leading at Periyamalai.
|
2.40
|
Hindu Religious & Endowment Board
|
Work is in Progress
|
--
|
5
|
Construction of Dormitory block for public use at Periyamalai.
|
10.50
|
Hindu Religious & Endowment Board
|
Administrative sanction got from Commissioner, Hindu Religious & Endowment Board
|
--
|
Total
|
32.37
|
N.B: Construction of Guest Room at Foot of the hill of Periyamalai
Rs.20.00 lakhs ( Rs.52.37lakhs – Rs.20.00lakhs = Rs.32.37lakhks )