Yelagiri Tourism Dev Progress report




PROGRESS REPORT AS ON 22.9.2010

S.
No
Name of Work

Estimate Cost
Executing Agency
Stage of
Work
Remarks
1.
Amphi Theatre at New Summer Festival Ground
42.00
Project Director, D.R.D.A., Vellore-9.
Completed. 
--
2.
Watch Tower with boat jetty at Nilavour
19.71
Project Director, D.R.D.A., Vellore-9.
Completed
--
3.
Beautification of Path and Drive way to Boating lake at Punganoor
83.63
Project Director, D.R.D.A., Vellore-9.
Completed
--
4.
Auditorium at New Summer Festival Ground
40.43
Project Director, D.R.D.A., Vellore-9.
Completed

--
5.
Information Kiosks, Beautification of entrance and toll gate
20.45
Project Director, D.R.D.A., Vellore-9. (Kattidamaiyam)
Completed
--
6.
Deepening the lake widening of Foot Path alround the lake and strengthening the lake bund
55.36
Project Director, D.R.D.A., Vellore-9.
Completed
--
7.
High mast lighting in and around the lake & Street Light Provision
27.77
BDO, Jolarpet.
Completed
--
8.
Construction at Hanging Pedestrain bridge at hanuman temple before hair pin bend No 8  in Elagiri Hills
17.30
Project Director, D.R.D.A., Vellore-9.
Completed
--
9.
Construction of Trekking shelter on Jalagambarai Nilavoor Trail with Camping facilities 3 units Elagiri Hills
2.10
District Forest Officer Tirupathur
Completed
--
10.
Construction of Rain Shelter 1 unit at hairpin bend  No 9 in Elagiri Hills
0.70
District Forest Officer Tirupathur
Completed
--
11.
Development of view point at Karadi munai in Elagiri Hills
1.90
District Forest Officer Tirupathur
Work in progress
--
12.
Adventure & Sports facilities at Elagiri hills

11.75
Project Director, D.R.D.A., Vellore-9.
Completed
--
13.
Adventure & Sports facilities providing swimming pool at Elagiri Hills

18.62
Project Director, D.R.D.A., Vellore-9.
Completed
--
14.
Fencing using weldmesh with L Angle post alround boating lake at Elagiri Hills

18.00
Project Director, D.R.D.A., Vellore-9.
Completed
--
15.
Fencing Using Weldmesh with L Angle post alround Yatri Nivas and information centre (Kattidamaiyam) at Elagiri Hills
6.00
Project Director, D.R.D.A., Vellore-9.
Completed
--

Total
365.72








State Funded Scheme 50 %, (Tourism Department Sanction )
G.O Ms.No 182 Tourism & Culture Department (T3)  Progress Report as on 22.9.2010
Infrastructure Facilities to Elagiri Hills  

S.
No
Name of Work

Estimate Cost
(in lakhs)
Executing Agency
Stage of
Work
Remarks
1
Providing CC pavement at Athanavoor to Pallakanniyur Km 0/0-1/9 in Elagiri Hills

41.90
Project Director, D.R.D.A., Vellore-9.
Work Completed
--
2
Nilavoor to Pallakaniyur BT Road  0/0-2/0

35. 90
Project Director, D.R.D.A., Vellore-9.
Work Completed
--
3
Nilavoor Boat House foot path around  
10.90
BDO, Jolarpet
Work Completed

--
4
Information centre to summer festival ground foot path 800 M

21.50
Project Director, D.R.D.A., Vellore-9.
Work Completed
--
5
Nilavur  Boat House around retaining wall

22.15
BDO, Jolarpet
Work Completed
--
6
Nilavur Boat House around fencing work

8.50
BDO, Jolarpet
Work Completed
--

Total
140.85









POOLED ASSIGNED REVENUE SCHEME 2008-2009

Sl.
No.
Name of the Habitation
Name of the Work
Estimate Amount
(Rs. in lakhs )
Stage of Work
1.
2.
3.
4.
5.
1.
Elagiri Hills
Construction of Check Dam in Erimeri vattam in Nilavoor
2.92
Completed
2.
Elagiri Hills
Construction of Check Dam in Melarikottai in Mangalam
6.42
Completed
3.
Elagiri Hills
Construction of Check Dam in Thayalur
8.25
Completed
4
Elagiri Hills
Construction of Check Dam in Alamarathuvattam 
5.65
Completed
5.
Elagiri Hills
Construction of Check Dam in Manjankollai Pudur.
6.50
Completed
6
Elagiri Hills
Construction of Check Dam in Muthanur Odai.
7.32
Completed
7
Elagiri Hills
Construction of Check Dam in Military Camp in Mettukaniyur
8.25
Completed
8
Elagiri Hills
Construction of Check Dam in Melarikottai Vt.near Eswaran koil.
8.25
Completed
9
Elagiri Hills
Construction of Check Dam in Rayaneri.
6.50
Completed
10
Elagiri Hills
Construction of Check Dam in Kottur Ebinesar School back
7.32
Completed
11
Elagiri Hills
Construction of Check Dam in Aurovil near Leemeridian in Kottur.
8.25
Completed
12
Elagiri Hills
Construction of Check Dam in Ambalathupallam in Pallakaniyur.
8.75
Completed
13
Elagiri Hills
Construction of Check Dam in Puthur in Padanoor Village
8.75
Completed
14
Elagiri Hills
Construction of Check Dam in Erimeri vattam in Puthur.
14.11
Completed
15
Elagiri Hills
Construction of Check Dam in Thayalur Burial Ground
8.75
Completed
16
Elagiri Hills
Construction of Check Dam in Near in Mangalam Burial Ground
8.75
Completed.
17
Elagiri Hills
Construction of Check Dam in Karikkuthi Eri in Athanvur Village
8.75
Completed
Page -2

POOLED ASSIGNED REVENUE SCHEME 2008-2009


Sl.
No.
Name of the Habitation
Name of the Work
Estimate Amount
(Rs. in lakhs )
Stage of Work
18
Elagiri Hills
Beautification & improvements to Mangalam Eri Boat House and Park

15.44
Completed
19
Elagiri Hills
Beautification & improvements to Nilavur (Kotooran ) Eri

15.42
Completed
20.
Elagiri Hills
Beautification & improvements to Manjankollai Eri Boat House and Park

12.20
Completed
21
Elagiri Hills
Providing CC road to Mangalam Samartian School to K.Vattam Road

12.33
Completed
22.
Elagiri Hills
Providing CC road to Manjankollai to Krishnan Vattam

26.50
Completed
23.
Elagiri Hills
Providing CC road to Manjankollai to Krishnan Vattam

2.12
Completed
24.
Elagiri Hills
Construction of Check Dam in 30 mt length Mangalam Melkollai (near Ex.president land)

8.85
Completed
25.
Elagiri Hills
Construction of Oor Eri in Athanavoor.

14.22
Completed


Total


240.57



TOURISM DEVELOPMENT WORKS
G.O.No 160 Tourism and Culture (S3) Department Dated : 4.9.2008
   PROGRESS REPORT AS ON 22.9.2010
SHOLINGHUR SHRI LAKSHMI NARASIMA SWAMY TEMPLE
TOURISM CONTRIBUTION Rs.16.18 Lakhs, H & RC Contribution : Rs.36.19 Lakhs.
                                                                                                                                                  
S.
No
Name of Work

Estimate Cost
Executing Agency  
Stage of
Work
Remarks
1
Car Parking at Chinna Malai Adivaram


11.75
Hindu Religious & Endowment Board

Work Completed

--
2
Car Parking at Periya Malai Adivaram


5.47
Hindu Religious & Endowment Board

Work Completed.

--
3
Construction of Toilet Block at Chinamalai, 

2.25
Hindu Religious & Endowment Board

Work Completed

--
4
Construction of  toilet at 620th Step leading at Periyamalai.


2.40
Hindu Religious & Endowment Board

Work is in Progress

--
5
Construction of Dormitory block for public use  at Periyamalai.

10.50
Hindu Religious & Endowment Board
Administrative sanction got from Commissioner, Hindu Religious & Endowment Board

--

Total
32.37






N.B:  Construction of Guest Room at Foot of the hill of Periyamalai
          Rs.20.00 lakhs ( Rs.52.37lakhs – Rs.20.00lakhs = Rs.32.37lakhks )